Lesson Learned





By: Drilling Engineer

Report No.

2401

Discipline/Origin

Drilling
Own Experience

Well

Hemispheres
36/1-4

Date created

2021/12/30
1438 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Logistics
Negative

Borgland Dolphin


What happened in Production section:
ALL mud skips was put on the same boat, effectively removing any hope for recieving backload on said boat. When a rig and the boat is full, no one has the space to move around items needed. And a boat that is unable to take backload is a useless boat.

What Was Planned

Bring out mud skips for the upcoming drilling with OBM

What Was Learned

25% of deck space shall be reserved each sail for rig backload.

What Actions Are Required

No actions required.

I have informed all parties at logistics meeting.